ISSN 2096-4498

   CN 44-1745/U

二维码

Construction Control Technologies for Shield Tunnel Boring in  Waterrich Fine Silty Sand Strata and Parallel Crossing Underneath  Pressured Watersupply Pipeline

  • WAN Junfeng
Expand
  • (1. China Railway Tunnel Group Co., Ltd., Luoyang 471009, Henan, China;  2. China Railway Tunnel Stock Co., Ltd., Zhengzhou 450001, Henan, China)

Received date: 2015-09-11

  Revised date: 2016-01-27

  Online published: 2016-04-27

Abstract

The Guojilu StationNorth Huanchenglu Station shield bored tunnel on Zhengzhou Metro Line No. 2 is located in waterrich fine silty sand strata and crosses underneath 3 existing pressured watersupply concrete pipelines. In order to meet the settlement control requirements, the construction risk of soil deformation induced by heterogeneous settlement is analyzed. The cutterhead structure type, cutterhead support type and injection points of ground conditioning agent on cutterhead are the main factors for ground settlement. Some suggestions are propased as follows: 1) The shield cutterhead structure type and related devices are very important. 2) Rational construction parameters and technologies are necessary. The monitoring results show that the maximum pipeline settlement can meet the risk control requirement.

Cite this article

WAN Junfeng . Construction Control Technologies for Shield Tunnel Boring in  Waterrich Fine Silty Sand Strata and Parallel Crossing Underneath  Pressured Watersupply Pipeline[J]. Tunnel Construction, 2016 , 36(4) : 439 -443 . DOI: 10.3973/j.issn.1672-741X.2016.04.011

Outlines

/

〈 〉