Advanced Doubledrift Construction Technologies for Taoshuping Tunnel Crossing Waterrich Fine Silty Sand Strata

  • ZHANG Xuewen
Expand
  • (Headquarters of LanzhouChongqing Railway Project, China Railway Construction Bridge Engineering Bureau Group Co., Ltd., Longnan 748500, Gansu, China)

Received date: 2015-03-26

  Revised date: 2016-02-27

  Online published: 2016-05-25

Abstract

Taoshuping tunnel on LanzhouChongqing Railway is a Grade Ⅰ doubleline railway tunnel; it crosses waterrich fine silty sand strata. The surrounding rocks of the tunnel are bad and unstable. During the construction of Taoshuping Tunnel, large water inrush and softening of waterrich fine silty sand strata occur. As a result, doubledrift method is adopted to carry out drainage construction. The technical problem of the excavation of tunnel crossing waterrich fine silty sand strata has been solved and the deformation of primary support has been brought under effective control.

Cite this article

ZHANG Xuewen . Advanced Doubledrift Construction Technologies for Taoshuping Tunnel Crossing Waterrich Fine Silty Sand Strata[J]. Tunnel Construction, 2016 , 36(5) : 577 -584 . DOI: 10.3973/j.issn.1672-741X.2016.05.013

Outlines

/

〈 〉