Key Construction Technologies for Curved Jacking Pipe Roofing of Gongbei Tunnel
Received date: 2016-02-01
Revised date: 2016-03-09
Online published: 2016-08-17
The construction difficulties of curved jacking pipe roofing of Gongbei Tunnel under complex soft soil, high groundwater pressure and sensitive environment conditions are analyzed. The technologies adopted include pipe jacking machine selection, launching and receiving under high groundwater pressure technology, accuracy control of small span curved jacking, pipeline structure and sealing test and treatment of pipe jacking slurry and obstacles. Good effects have been achieved.
ZHANG Peng , PAN Jianli , LIU Yingliang , MA Baosong . Key Construction Technologies for Curved Jacking Pipe Roofing of Gongbei Tunnel[J]. Tunnel Construction, 2016 , 36(8) : 968 -975 . DOI: 10.3973/j.issn.1672-741X.2016.08.012
/
| 〈 |
|
〉 |