Deviation Rectification Technologies for Segment Installation  of Honggu Tunnel in Nanchang

  • XIE Zhenling ,
  • HE Xiaobo
Expand
  • (Jiangxi ZhongChang Engineering Consultation and Supervision Co., Ltd., Nanchang 330038, Jiangxi, China)

Received date: 2016-05-06

  Revised date: 2016-08-04

  Online published: 2016-09-20

Abstract

The sinking and installation technologies for Honggu Tunnel in Nanchang are introduced. The influencing factors of deviation of tunnel segment and deviation rectification methods are summarized. The horizontal dislocation method and segment tail swing method are adopted for deviation rectification of tunnel segment of Phase 1 of Honggu Tunnel. The construction effect is good. Suggestions are given for axial line control of tunnel segment sinking of Phase 2 of Honggu Tunnel in terms of steel end shell manufacturing accuracy, horizontal flow velocity and segment sinking monitoring accuracy.

Cite this article

XIE Zhenling , HE Xiaobo . Deviation Rectification Technologies for Segment Installation  of Honggu Tunnel in Nanchang[J]. Tunnel Construction, 2016 , 36(9) : 1106 -1113 . DOI: 10.3973/j.issn.1672-741X.2016.09.012

Outlines

/

〈 〉