Application of Ground Surface Pregrouting to Water  Inrush Prevention and Control for Shafts

  • YAO Weijing ,
  • PANG Jianyong ,
  • ZHANG Jinsong ,
  • XU Lei
Expand
  • (School of Civil Engineering and Architecture, Anhui University of Science and Technology,  Huainan 232001, Anhui, China)

Received date: 2016-08-15

  Revised date: 2016-11-16

  Online published: 2017-06-08

Abstract

The Zhangji Mining Area is located in the crack fractured zone and with rich water. The ground surface pregrouting of auxiliary shaft No. 2 is difficult. Hence, the construction technology of ground surface pregrouting is studied based on engineering geological investigation, technical design and industrial experiment. A series of technologies, i.e., freezing construction of upper strata, pregrouting of lower bedrock, and vertical boreholes and Yshaped boreholes combined layout method, are adopted, which leads to simultaneous construction of grouting, freezing and shaft sinking and shortening of construction period. Meanwhile, realtime monitoring has been realized and key grouting parameters have been obtained by using selfdeveloped monitoring device. The construction effect is estimated by pressurized water test. The monitoring results show that: 1) The final grouting pressure value and grouting quantity can meet the design standards, and the total grouting quantity was 16 286 m3. 2) The permeability coefficient of formation decreased obviously and the residual water inflow of the mine shaft is 2.27 m3/h obtained from the pressurized water test, which proves the rationality and efficiency of the abovementioned method in terms of reinforcement and water stopping.

Cite this article

YAO Weijing , PANG Jianyong , ZHANG Jinsong , XU Lei . Application of Ground Surface Pregrouting to Water  Inrush Prevention and Control for Shafts[J]. Tunnel Construction, 2017 , 37(5) : 630 -636 . DOI: 10.3973/j.issn.1672-741X.2017.05.016

Outlines

/

〈 〉