Comprehensive Treatment Scheme and Construction Technologies for Superlarge Karst Tunnel

  • WANG Shaohui ,
  • CHEN Zhao ,
  • JIANG Chong ,
  • LONG Haijian ,
  • LIU Lin ,
  • PENG Xiaolin ,
  • SHA Ce
Expand
  • (1. No.1 Engineering Co., Ltd. of FHEC of CCCC, Beijing 102205, China;2. Hunan Provincial Communications Planning, Survey & Design Institute Co., Ltd., Changsha 410008, Hunan, China; 3. School of Resources and Safety Engineering, Central South University, Changsha 410083, Hunan, China)

Received date: 2017-03-13

  Revised date: 2017-05-26

  Online published: 2017-07-02

Abstract

Superlarge karst caves are encountered during construction of Naqiu Tunnel on Yongji Highway. As a result,a combination structure of bearing pile foundation + vertical and horizontal framebeamplate structure + reinforced concrete retaining wall and slag backfilling are adopted based on characteristics and treating difficulties of large karst cave and theoretical and site studies. And then a set of construction methods of alternate updown construction of the structure on basis of slag backfilling is established. The construction practice shows that the technologies used are rational and feasible and good effect has been achieved.

Cite this article

WANG Shaohui , CHEN Zhao , JIANG Chong , LONG Haijian , LIU Lin , PENG Xiaolin , SHA Ce . Comprehensive Treatment Scheme and Construction Technologies for Superlarge Karst Tunnel[J]. Tunnel Construction, 2017 , 37(6) : 748 -752 . DOI: 10.3973/j.issn.1672-741X.2017.06.015

Outlines

/

〈 〉