Study of Method of Dredging Construction for Immersed Tunnel with Furrow Gravel Cushion Foundation

  • FENG Haibao ,
  • YIN Gang
Expand
  • (1. State Key Laboratory of Hydraulic Engineering Simulation and Safety, Tianjin University, Tianjin 300072, China; 2. School of Civil Engineering, Tianjin University, Tianjin 300072, China; 3. No.2 Engineering Company Ltd. of CCCC First Harbor Engineering Company Ltd., Qingdao 266071, Shandong, China; 4. Shanghai Zhenhua Heavy Industry Co., Ltd., Shanghai 200125, China)

Received date: 2016-11-04

  Revised date: 2017-09-07

  Online published: 2018-02-01

Abstract

The dredging construction for the immersed tunnel with furrow gravel cushion foundation should be carried out. As a result, new type of dredging methods and equipments, with no disturbance to top of gravel cushion foundation, are developed for immersed tunnel with furrow gravel cushion foundation by analytical calculation, physical model test and numerical simulation considering construction environments and conditions. By adopting the abovementioned methods and equipments, the dredging construction of the rubble furrow and furrow top can be carried out, rapid dredging construction can be realized and construction risk can be reduced.

Cite this article

FENG Haibao , YIN Gang . Study of Method of Dredging Construction for Immersed Tunnel with Furrow Gravel Cushion Foundation[J]. Tunnel Construction, 2018 , 38(1) : 86 -90 . DOI: 10.3973/j.issn.2096-4498.2018.01.011

Outlines

/

〈 〉