ISSN 2096-4498
CN 44-1745/U
ISSN 2096-4498
CN 44-1745/U
Analysis of Transverse Ground Settlement and Pipe Interaction of Superlarge Pipe Roofing in Gongbei Tunnel
Received date: 2017-11-03
Revised date: 2018-04-24
Online published: 2018-10-26
In order to study the ground settlement law and the interaction between jacking pipes during smallspacing circumferential group pipe jacking, the ground settlement caused by pipejacking is analyzed, and the value of ground loss ratio and the empirical formula of settlement trough width coefficient during smallspacing circumferential group pipe jacking are put forward by taking the piperoofing project of Gongbei Tunnel of Zhuhai Connection Line of Hong KongZhuhaiMacau Bridge for example. And then the influence of fore pipejacking group on strata loss and maximum ground settlement induced by followed pipejacking group is analyzed by numerical simulation. The analytical results show that: (1) The ground settlement caused by the pipe jacking of Gongbei Tunnel is within the control requirements. (2) With the increase of buried depth of the pipe, the settlement trough width coefficient caused by the single pipe increases, while the maximum ground settlement decreases; the initial ground loss ratio during pipe jacking is 1.5%. (3) Due to the promotion of technical proficiency and the reinforcement effect of fore pipejacking group, the average ground loss ratio after jacking of all 37 pipes is ultimately controlled to 0.8%, and the ground settlement has been effectively controlled.
LIU Yang , SHI Peixin , PAN Jianli , YU Caicheng . Analysis of Transverse Ground Settlement and Pipe Interaction of Superlarge Pipe Roofing in Gongbei Tunnel[J]. Tunnel Construction, 2018 , 38(10) : 1680 -1687 . DOI: 10.3973/j.issn.2096-4498.2018.10.012
/
| 〈 |
|
〉 |