Problems and Countermeasures for Doubleshield  TBM Applied in Shenzhen Metro

  • SONG Tiantian ,
  • LI Hongbo ,
  • CHEN Gang
Expand
  • (1. Shenzhen Metro Group Co., Ltd., Shenzhen 518000, Guangdong, China; 2. State Key Laboratory of Shield Machine and Boring Technology, Zhengzhou 450000, Henan, China; 3. China Railway Tunnel Group Co., Ltd., Guangzhou 511458, Guangdong, China)

Received date: 2019-01-16

  Revised date: 2019-06-17

  Online published: 2019-07-02

Abstract

The doubleshield TBM applied in urban metro construction is always accompanied by difficulties such as difficult launching, limited small radius, crossing extremelyhard rock and fault and fracture zone. Hence, the problems and countermeasures for doubleshield TBM applied in Shenzhen Metro construction are studied. Four aspects are proposed as follow: (1) Cutting tool wear and consumption rules, advancing control measures and solution of measuring platform vibration in the construction of doubleshield TBM with limited small turning radius about 260 m; (2) a separate launching technical scheme solving the problem of limited space; (3) targeted design of doubleshield TBM and improvements for cutting tool under 210 MPa extremelyhard rock condition; (4) tunneling parameters and countermeasures for doubleshield TBM crossing fault fracture zone.

Cite this article

SONG Tiantian , LI Hongbo , CHEN Gang . Problems and Countermeasures for Doubleshield  TBM Applied in Shenzhen Metro[J]. Tunnel Construction, 2019 , 39(6) : 998 -1004 . DOI: 10.3973/j.issn.2096-4498.2019.06.013

Outlines

/

〈 〉