Prediction and Analysis of Long-term Settlement of Large Cross-section Quasi-rectangular Combined Pipe Jacking Excavated Station in Soft Soil
Received date: 2019-09-26
Online published: 2020-04-04
The post-construction long-term settlement of a large cross-section small-spacing pipe jacking tunnel in soft soil is predicted and analyzed to ensure its safety and stability during construction and operation. The two-dimensional numerical analysis method with the soft soil creep constitutive model is used to establish an analysis model for the longterm settlement of the combined pipe jacking structure; and the development of the long-term settlement of the surface, combined pipe jacking structure and soil is analyzed. The analytical results show that: (1) The long-term settlement of surface and combined pipe jacking structures develops fast in the early stage, but slows down with time; and the time for stabilization is quite long. (2) The long-term settlement of the surface is large in the middle and small on sides, and the maximum settlement value is 28. 4 cm in 20 years. (3) The long-term settlement of the east line station and that of the west line station are relatively coincide with each other, the settlement value is 8. 9 cm, and the settlement of west line station hall, in contrast, is significant and the settlement value reaches 22. 4 cm.
YANG Yifeng , LIAO Shaoming , WU Dongpeng . Prediction and Analysis of Long-term Settlement of Large Cross-section Quasi-rectangular Combined Pipe Jacking Excavated Station in Soft Soil[J]. Tunnel Construction, 2019 , 39(S2) : 213 -219 . DOI: 10.3973/j.issn.2096-4498.2019.S2.028
/
| 〈 |
|
〉 |