In order to solve the problem that the shield cannot
receive normally due to size restriction of the receiving end in narrow space,
it is necessary to take auxiliary measures to disassemble the main parts and
then transport them back to launching shaft along the original shield tunnel
and lift them out. A 6 680 mm shield is adopted in the
left line between Pinganli Station and Jishuitan Station of Beijing Metro Line
19 Phase Ⅰ Project, through the study on the size and
embedded design of the receiving end, the disassembly scheme and sequence in
mined space, the auxiliary hoisting technology during the disassembly process,
the construction period management and other aspects, the shield disassembly
scheme and control points in narrow and mined space are summarized, and the
emphasis and difficulties and key technologies of disassembly are analyzed. The
results show that the technology ensures the construction safety and progress,
solves the technical and safety problems for shield construction in narrow and
mined space.
KOU Dingtao, SUN Jian
.
Study on Dismantle Technology of 6
680 mm Shield
in Narrow Mined Tunnel
[J]. Tunnel Construction, 2020
, 40(S1)
: 404
-412
.
DOI: 10.3973/j.issn.2096-4498.2020.S1.053