Key Technologies for TBM Jamming Release of Gaoligongshan Tunnel under Unfavorable Geologies

  • WANG Yafeng
Expand
  • (China Railway Tunnel Stock Co., Ltd., Zhengzhou 450001, Henan, China)

Online published: 2021-04-05

Abstract

 In this study, to reduce the risk of TBM jamming under unfavorable geologies and perform a fast jamming release, an evaluation of key technologies is performed, including geological forecast, tunneling parameters control, primary support, antijamming measures, jamming release, advance reinforcement, and ground conditioning of unfavorable geologies (such as lithologic contact zone, fault fracture zone, fullyweathered granite and siltyfine sand formation, water gushing, and highpressure waterrich weak broken altered structural belt). Moreover, the relationship between the tunneling parameters and TBM jamming is obtained, and control measures are presented. Meanwhile, certain countermeasures corresponding to different scales of unfavorable geologies, i.e. cutterhead cleaning, cyclic pipe roof, pilot tunnel, and bypass heading methods, are summarized.

Cite this article

WANG Yafeng .

Key Technologies for TBM Jamming Release of Gaoligongshan Tunnel under Unfavorable Geologies

[J]. Tunnel Construction, 2021 , 41(3) : 441 -448 . DOI: 10.3973/j.issn.2096-4498.2021.03.013