ISSN 2096-4498

   CN 44-1745/U

二维码

Replacement Technology of ConcreteFilled Steel Tubular Columns in Method Station Excavated by CutandCover TopDown Method

  • NIU Bin
Expand
  • (Beijing Urban Construction Design & Development Group Co., Limited, Beijing 100037, China)

Online published: 2021-07-01

Abstract

For a metro station constructed with the cutandcover topdown method, if the perpendicularity of the concretefilled steel tubular columns does not meet the requirements of relevant specifications, the perpendicularity deviation must be corrected. The perpendicularity deviations of the concretefilled steel tubular columns of the first underground floor to the third underground floor toward  the horizontal crosssection direction of the station reach 114, 254, and 375 mm, respectively, those toward longitudinal direction reach 44, 68, and 93 mm, respectively, which is beyond relevant requirements, showing that concretefilled steel tubular columns should be replaced. The main measures adopted are as follows: (1) temporary support is provided for the replacement structure by the joint support of concrete and steel tubular columns; (2) when removing the concretefilled steel tubular columns, a combination of static and manual removal is used to retain the original beams and steel bars in the plate; (3) the newlyadded steel pipe top reinforcement ring and the original reinforcement ring of column top of the first underground floor are tightened, bolted, and welded to ensure the reliability of the connection; and (4) the automatic deformation and strain monitoring should be conducted during the whole construction process. The practice shows that the replacement scheme is reasonable and feasible.

Cite this article

NIU Bin .

Replacement Technology of ConcreteFilled Steel Tubular Columns in Method Station Excavated by CutandCover TopDown Method

[J]. Tunnel Construction, 2021 , 41(6) : 1032 -1038 . DOI: 10.3973/j.issn.2096-4498.2021.06.016

Outlines

/

〈 〉