To study the prefabricated structure force of the
assembled station entrance ring frame and develop a theoretical foundation for
the design of the entrance and exit ring frame, the load modes of the
prefabricated ring frame of a prefabricated station are analyzed from
construction to usage. The stress properties of the ring frame structure are
examined utilizing the finite element method from the construction and
installation stage to the backfilling stage toward the completion stage of the
entrance and exit. Furthermore, it is observed that after joint grouting, the
concave and convex tenon grooves between the prefabricated ring frame structure
and roof structure generates a whole along longitudinal direction of the
station, which is beneficial to the ring frames′ stress.
Meanwhile, in the soil covering stage and longterm
usage stage, the prefabricated ring frame structure and roof generate a whole
to collectively resist the various loads, which can meet the requirements of
the assembled station construction and the overall force requirements of the
station structure in advanced stages. Finally, a safety reserve method is
provided for constructing temporary steel support, and the structural stress is
examined to ensure the safety and reliability of the continuous assembly of the
entrance and exit rings.
WU Chenggang
,
LUO Jiejun
,
LIN Fang
. Stress Analysis of Prefabricated Structure of Entrance and Exit Ring Frame along Longitudinal Direction of Station[J]. Tunnel Construction, 2022
, 42(3)
: 414
-419
.
DOI: 10.3973/j.issn.2096-4498.2022.03.009