Blasting disturbance for tunnels excavated using bench
method greatly influences the stability of the overlying surrounding rocks.
This may result in tunnel collapse in the case of minimal overburden thickness.
Thus, to address the above problem, an inverse bench excavation method, i.e., the
lower bench goes first and then the top heading is excavated by blasting
control technique, is proposed. The stability of surrounding rocks excavated by
inverse bench method is numerically simulated using a case study of a metro
tunnel excavation in Qingdao by applying the FLAC 3D finite element analysis
software. The simulation results and engineering practice show that, under
minimal overburden thickness, the inverse bench excavation can provide extra
excavation free face for the top heading. This effectively reduces the blasting
disturbance to the mechanical properties and integrity of the surrounding
rocks, protecting their bearing capacity and guaranteeing the excavation safety
of the metro tunnel.
WANG Jianhui
,
GAO Meng
,
WANG Runsheng
,
YANG Kai
,
HUANG Changxin
,
ZHANG Lianzhen
,
ZHANG Qing
,
ZHAO Yao
,
HAN Xu
,
ZHAO Junyun
,
WANG Anni
,
LI Zhipeng
,
WENG Xianjie
. Stability Analysis of Surrounding Rock of Inverse
Bench Excavation of Metro Tunnel with Minimal
Overburden Thickness[J]. Tunnel Construction, 2023
, 43(4)
: 690
-697
.
DOI: 10.3973/j.issn.2096-4498.2023.04.015