To optimize the
construction of the prefabricated station effectively and improve the accuracy
of equipment lifting, the key construction technologies of the prefabricated
station are studied with a case study of the Shizhongyiyuan station of the
second phase of Shenzhen metro line 13. The section design of assembled
components, prefabrication quality control of components, transportation
equipment selection, and transportation process control, onsite
construction site layout requirements, design and selection of highprecision gantry crane, design optimization of lifting process,
selection of foundation reinforcement treatment scheme during construction,
precision control of fine flat belt construction, accurate lifting and
positioning of large volume components, tension process optimization and
quality control, grouting process optimization and process quality control,
sidewall fertilizer tank backfilling, and waterproof quality control are
summarized and optimized, and core technical data such as technical parameters,
lifting technical parameters, and tension parameters of highprecision gantry crane are obtained. The problems such as uneven
settlement, untightness of fertilizer tank backfill, and leakage are summarized
and analyzed, and the solutions are proposed.
ZHOU Zhihui, SUN Bo
. Research on Key Technology of Prefabricated Metro -Station
with Internal Support System[J]. Tunnel Construction, 2023
, 43(S1)
: 464
-472
.
DOI: 10.3973/j.issn.2096-4498.2023.S1.054