When the underground structures and buildings of rail
transit do not match the renovation requirements, they should be expanded or
even reconstructed. According to various reconstruction requirements, key
technical difficulties in the design of the expansion and reconstruction of the
existing metro entrance and exit are summarized. In this study, a case study is
conducted on the reconstruction structure design of the entrance B of the
Huangmugang station of the Shenzhen metro line 7. First, the overall
construction of a sunken square is presented in terms of stationcity
integration, fire protection design, operational organization, antiflooding capacity, landscape design, structural construction method,
total duration, and investment of the transit oriented development(TOD)
project. Then, the design of foundation pit support with the same depth of
adjacent metro entrance, the existing station sidewall opening without reserved
connection conditions, and the connection structure node of new and existing
concrete are analyzed. The research results show the following: (1)
Demonstration should be fully implemented before renovation, the structure and
construction organization should be designed considering specific requirements,
and antiflooding and emergency plan should be
determined. (2) When constructing a foundation pit adjacent to the metro
entrances and exits, the existing enclosure and reserve backpressure soil can
be used to control the deformation of the entrances and exits and the
surrounding buildings, and the structural deformation should be closely
monitored, achieving informatized construction. (3) The floor unloading and
sequential construction can be used to demolish the sidewall of the existing
structure without reserved connection and temporary support conditions.
Beam/column structures can be constructed to connect with the existing
structure, and waterproof measures should be implemented.
ZHANG Chenming, YANG Li, ZHANG Wenting, ZHANG Xixun, SHI Dan, LI Runnan
. Structural Design of Reconstructing Metro Entrance and
Exit to Sunken Squares[J]. Tunnel Construction, 2023
, 43(S2)
: 378
-386
.
DOI: 10.3973/j.issn.2096-4498.2023.S2.042