By analyzing
the framework and model correspondence between the IFC and the APDL command,
the corresponding process of the two is analyzed. A rapid transformation method
from tunnel engineering parameterized BIM model to ANSYS finite element model
is proposed, the software was developed by using C# programming language. The
main conclusions are as follows: (1) The generated IFC model can be viewed in
BIM Vision. The model can be submitted to the construction and operation party
for effective utilization; (2) By modifying the tunnel size parameters to
generate the corresponding IFC model and the APDL command flow model, 95% of
the modeling time is saved; (3) Designers can further modify the generated APDL
command stream to conduct static, modal, and dynamic analysis of tunnel
structures. The analysis results can effectively guide engineering design; (4)
The integrated parameterized modeling software is userfriendly
and can be extended to complex underground engineering applications, improving
the efficiency of BIM model generation and ANSYS structural calculation and
analysis.
LIU Shaopeng
. Research and Application of Fast Generation and
Transformation of BIMANSYS
Model in Immersed Tunnel[J]. Tunnel Construction, 2023
, 43(S2)
: 467
-476
.
DOI: 10.3973/j.issn.2096-4498.2023.S2.051