To lower the electricity
operational costs of highway tunnels, the application prospects of renewable
energy complementary power generation systems in highway tunnels are explored,
and suitable methods for solving capacity configuration are examined. Furthermore,
a complementary power generation system using wind, solar, water, and energy
storage devices to supply power to highway tunnels is established. Using a
particularly-long highway tunnel (total
length of 7.1 km) as the estimation model, an improved particle swarm
optimization algorithm, namely the discrete adaptive particle swarm
optimization algorithm, is employed. This algorithm is used for solving the
optimal capacity configuration of wind power, photovoltaic power, hydro power,
and energy storage devices, taking the minimal construction and equipment
maintenance costs over the entire lifecycle as the objective function and the
power shortage load rate and the state of the energy storage battery as
constraints. The results indicate the following: (1) Compared to the standard
particle swarm algorithm, the discrete adaptive particle swarm optimization
algorithm has lower total investment costs and stronger optimization
capabilities. (2) Compared to the tunnel′s annual
electricity costs, the initial investment will be recouped within 5 years. (3)
Over the 20-year full lifecycle of the equipment in the
wind-solar-water-energy storage complementary power generation system, the tunnel can
save 19.203 9 million yuan in terms of electricity costs.
LI Jin, LIN Zhi, YU Chongchong, YIN Heng, LIU Chaoming, HUANG Kexin
.
Capacity Configuration of Wind-Solar-Water-Energy Storage Complementary Power Generation System for Highway
Tunnels
[J]. Tunnel Construction, 2024
, 44(S1)
: 124
-130
.
DOI: 10.3973/j.issn.2096-4498.2024.S1.013