Vibrodensification Test and Particle Flow Simulation of Rock Cushion in Immersed Tunnels

  • FU Baiyong ,
  • SONG Shenyou ,
  • JIN Wenliang
Expand
  • (1. Department of Civil Engineering, Tsinghua University, Beijing 100084, China; 2. CCCC Highway Bridges National Engineering Research Center Co., Ltd., Beijing 100120, China; 3. Shenzhong Link Management Center, Zhongshan 528400, Guangdong, China)

Online published: 2025-06-20

Abstract

Flatness, vibrodensification parameters, and the post-treatment quality of rock cushions are critical to the success of vibrodensification operations in immersed tunnels. The authors combine field testing and particle flow numerical simulations to investigate the vibrodensification performance of rock cushions, using the Shenzhen-Zhongshan Link immersed tunnel as a case study. The effects of vibro-densification duration, cushion thickness, and vibration frequency on the densification behavior are examined, and the underlying mechanisms are interpreted from a microscopic perspective based on strong contact force chains. The main findings are as follows: (1) Cushion thickness is the dominant factor influencing the vibration-induced settlement of the rock cushion, while vibration frequency influences settlement within an optimal frequency range. (2) For rock particle sizes of 0.15–0.30 m, a cushion thickness of 1.2 m and a vibration frequency of 20 Hz, a vibro-densification time of 45 s yields better performance than durations of 20 s or 30 s. (3) At a cushion thickness of 1.2 m and a vibrodensification time of 45 s, the optimal performance is achieved with a vibration frequency of 20 Hz, outperforming frequencies of 10 Hz and 30 Hz. (4) For improved vibro-densification, a cushion thickness greater than 1.2 m is recommended under a vibration frequency of 20 Hz and a vibro-densification time of 45 s.

Cite this article

FU Baiyong , SONG Shenyou , JIN Wenliang .

Vibrodensification Test and Particle Flow Simulation of Rock Cushion in Immersed Tunnels

[J]. Tunnel Construction, 2025 , 45(6) : 1090 -1101 . DOI: 10.3973/j.issn.2096-4498.2025.06.004