Study on Discrete Element Modeling of Complete Construction
Process of Diversion Tunnel in Pianqiao Hydropower Station

Expand
  • 1. Jiulong Hydropower Development Co., Ltd.2. Southwest Jiaotong University

Received date: 2008-05-04

  Revised date: 2008-06-02

  Online published: 2009-11-17

Abstract

K2+010~+310 section of the diversion tunnel of Pianqiao Hydropower Station is located in heavily jointed rock mass. The surrounding rock mass has been greatly loosened and rockfall occurred due to delayed support after the excavation. In order to assure the tunnel stability and considering the tight construction period, the tunnel support is optimized and the worldwideused discrete element code UDEC is applied to simulate the complete tunnel construction and operation process so as to examine the stress and deformation distribution in rock mass at various stages of tunneling and to assess the optimized design of the tunnel support. Meanwhile, the simulation technology of tunneling and operation using UDEC is thus investigated.

Cite this article

LIANG Ziqiang, DENG Xifei, CHEN Shougen . Study on Discrete Element Modeling of Complete Construction
Process of Diversion Tunnel in Pianqiao Hydropower Station[J]. Tunnel Construction, 2009
, 29(1) : 45 -49,53 . DOI: A