Construction Technology for SuperShallowBuried Underground
Excavated Tunnels Crossing Underneath Freeway

Expand
  • China Railway Tunnel Survey &|Design Institute Co., Ltd.

Received date: 2008-10-28

  Revised date: 2008-12-29

  Online published: 2009-11-17

Abstract

 Dongganqu Tunnel in Luoyang new district is a large span shallowburied tunnel in weak stratum. Large piperoof presupport method, CRD method and assistant measures such as monitoring and information feedback are used in the tunnel excavation, which have achieved good effects in ensuring the construction safety and controlling the settlement of the freeway. This paper can provide reference for similar projects in the future.

Cite this article

XU Yajun . Construction Technology for SuperShallowBuried Underground
Excavated Tunnels Crossing Underneath Freeway[J]. Tunnel Construction, 2009
, 29(1) : 101 -104 . DOI: B