Construction Plan of Collapse Treatment of Nama Tunnel

Expand
  • China Railway 7th Engineering Bureau Group Co., Ltd.

Received date: 2007-09-04

  Revised date: 2007-11-19

  Online published: 2009-11-18

Abstract

 Due to the sudden change of the geological conditions, collapse occurs to the exit section of Nama tunnel, which is an integral part of QianGui railway capacityexpansion and reconstruction works. The situations, reasons and treatment construction plan of the collapse are presented. The construction practice shows that the collapse treatment plan is safe, reasonable and feasible and good results are achieved. The paper can provide reference for works construction under similar conditions in the future.

Cite this article

SHI Lei . Construction Plan of Collapse Treatment of Nama Tunnel[J]. Tunnel Construction, 2008 , 28(1) : 89 -92 . DOI: B