Construction Technology for Start Element of Castinsitu Continuous
Tshaped Girder of Daqiaoxiang Bridge

Expand
  • The 1st Engineering Co., Ltd of China Railway Tunnel Group

Received date: 2007-09-14

  Revised date: 2007-11-01

  Online published: 2009-11-18

Abstract

The start elements of Tshaped girder bridges, which have numerous embedded parts, concentrated pipes and complex structural stress, are critical parts of bridge construction. On basis of the construction of the start elements of Daqiaoxiang bridge, the author presents the design of the brackets and formworks, the tensioning of the prestressed boxes, the duct grouting technology, the construction of ordinary rebars and concrete casting.

Cite this article

DU Zhongqiu . Construction Technology for Start Element of Castinsitu Continuous
Tshaped Girder of Daqiaoxiang Bridge[J]. Tunnel Construction, 2008
, 28(1) : 110 -113 . DOI: B