Key Construction Technologies and Countermeasures for
Largescale Mined Interchange Metro Stations

  • CHEN Chao ,
  • DONG Xiao-Long
Expand
  • Shenyang Metro Headquarter

Received date: 2007-05-10

  Revised date: 2007-06-07

  Online published: 2009-12-04

Abstract

Taking the construction of Youth Street Station of Shenyang Metro as case history, the author presents the major construction steps and key points of PBA (PileBeamArch) construction method. Due to the complex structure of the Metro station, PBA (PileBeamArch) construction method is adopted, which improves the safety and stability of the works, minimizes the deformation occurring during construction and protects the adjacent structures and buildings effectively.

Cite this article

CHEN Chao , DONG Xiao-Long . Key Construction Technologies and Countermeasures for
Largescale Mined Interchange Metro Stations[J]. Tunnel Construction, 2007
, 27(3) : 71 -74,91 . DOI: B