Problems and Countermeasures for Tunnel Construction by
Doubleshielded TBMs in Adverse Geological Conditions

  • LIN Guo-Jing
Expand
  • China Railway 13th Bureau Group Co., Ltd.

Received date: 2007-02-25

  Revised date: 2007-03-26

  Online published: 2009-12-04

Abstract

Taking Shanggongshan tunnel on Zhangjiuhe River Water Diversion/Supply Project in Kunming, China as an example, the author analyzes such notorious adverse geological conditions as squeezing and/or swelling ground, fault and/or fracture zone, mud burst and water inflow that impede the boring of the doubleshielded TBMs and recommends options and countermeasures for these difficult geological conditions from the macro and micro viewpoints, which can provide reference for future tunnel construction by doubleshielded TBMs.

Cite this article

LIN Guo-Jing . Problems and Countermeasures for Tunnel Construction by
Doubleshielded TBMs in Adverse Geological Conditions[J]. Tunnel Construction, 2007
, 27(3) : 108 -111 . DOI: A

Outlines

/

〈 〉