ISSN 2096-4498

   CN 44-1745/U

二维码
wenzhang

Construction Technique on Stationcrossing Movement for Shield Machine

  • WANG Xun ,
  • YANG Bo ,
  • LIU Wen-Bin
Expand
  • China Railway First Bureau Group Co., Ltd.

Received date: 2007-05-31

  Revised date: 2007-06-11

  Online published: 2009-12-04

Abstract

It is a common working procedure that the shield machine should cross the completed station to get to the next section. It is a topic worth of considering how to cross the station fast, economically and effectively so as to ensure the schedule of the works and the safety of the equipment. The construction technique of the shield machine  HERRENKNECKT S285  crossing  Beigongmen station of No.20 bid section of line 4 of Beijing Metro is presented in the paper.

Cite this article

WANG Xun , YANG Bo , LIU Wen-Bin . Construction Technique on Stationcrossing Movement for Shield Machine[J]. Tunnel Construction, 2007 , 27(4) : 52 -54 . DOI: B