Construction Technology for Fillingtype Waterrich
Karst Caves in No.1 Dayaoshan Tunnel
Large scale water/mud inflow occurs at the face of No. 1 Dayaoshan tunnel on Wuhan~Guangzhou passengerdedicated railway when the construction of the tunnel reaches DK1909+624 and enters F6 fault. It is observed that a large fillingtype waterrich karst cave exists on the right side of the tunnel. The construction of the tunnel is carried out strictly in accordance with the principle of “water probing, pregrouting and installing forepoling pipe roofs, which are followed by tunnel excavation, radial compensation grouting and quick lining”. The concept of “drainage assisted by waterproofing” is adopted. For the sake of these principles and concepts adopted, the construction of the tunnel passes the karst cave with safety and high speed.
TUN Hai-Zhi
. Construction Technology for Fillingtype Waterrich
Karst Caves in No.1 Dayaoshan Tunnel[J]. Tunnel Construction, 2007
, 27(5)
: 72
-74,84
.
DOI: B
/
| 〈 |
|
〉 |