Construction Scheme of Mined Tunnels of
Dongdan Station of Line 5 of Beijing Metro

  • HU Xi-Bei
Expand
  • Project Headquarters of Contract Section 06 of Line 5 of Beijing Metro,
     China Railway Tunnel Group

Received date: 2005-08-29

  Revised date: 2005-11-10

  Online published: 2010-01-26

Abstract

In this article, different construction schemes of largescale underground mined Metro stations are studied. The advantages and disadvantages of central drift method, side drift method and central column method are compared. On basis of the actual conditions of Dongdan station, central column method is selected as the final construction method. The new excavation method, i.e. the central column method, is also described in the article, which can provide reference for future similar works.

Cite this article

HU Xi-Bei . Construction Scheme of Mined Tunnels of
Dongdan Station of Line 5 of Beijing Metro[J]. Tunnel Construction, 2006
, 26(1) : 44 -48 . DOI: B