Design and Construction of Fullbreadth Invert Bridges Adopted in
Construction of Baozhen Tunnel with Railbound Hauling System

  • ZHANG Qun-Jian
Expand
  • YichangWanzhou railway project, the No.1 Engineering Corp., Ltd., the No.5
    Bureau Group, C.R.E.C.

Received date: 2005-12-05

  Revised date: 2006-01-25

  Online published: 2009-12-09

Abstract

On basis of the construction of Zhenbao tunnel on YichangWanzhou railway, the article introduces the design and construction of fullbreadth invert bridges adopted in the construction of the tunnel, in which railbound hauling system is adopted. By means of the introduced invert bridge, fullbreadth invert concrete casting is conducted with the present machinery and equipment. The article provides references both for the promotion of fullbreadth invert concrete casting and for the elimination of the operation diseases of tunnels.

Cite this article

ZHANG Qun-Jian . Design and Construction of Fullbreadth Invert Bridges Adopted in
Construction of Baozhen Tunnel with Railbound Hauling System[J]. Tunnel Construction, 2006
, 26(2) : 27 -29 . DOI: B