Treatment of Landslide at Tunnel Portals
Received date: 2006-01-16
Revised date: 2006-02-27
Online published: 2009-12-09
During the top heading construction of Matijing tunnel on GanzhouLongyan railway, huge deformation occurs to the 30mlong exit portal section, which is followed by full collapse. Several treatment options are attempted, but unfortunately no success is achieved. After thorough geological investigations, it is determined that there exist landslide, on basis of which comprehensive treatment plan is prepared. The article presents the landslide treatment method, demonstrating the great importance of thorough geological investigations in tunnel engineering works.
Key words: tunnel landslide comprehensive treatment
LIN Sanguo . Treatment of Landslide at Tunnel Portals[J]. Tunnel Construction, 2006 , 26(3) : 73 -75 . DOI: B
/
| 〈 |
|
〉 |