Study on EPB Shield Machine Construction Technology under Complex
Geological Conditions Achieved in Guangzhou Metro
Received date: 2005-12-01
Online published: 2010-04-21
Due to the complex geological conditions of Guangzhou Metro project, for example the shield machines need to bore through karst caves and highstrength granite and cross underneath the Pearl River, a lot of shield machine construction experience has been accumulated during the construction, while numerous difficult problems have been encountered. The article makes an analysis on the geological conditions of Guangzhou Metro project and makes a study on and summary of the EPB shield machine construction technology under complex geological conditions.
Key words: Metro shield machine boring technology
DU Jian-Hua
,
CHEN Gong-Yun
. Study on EPB Shield Machine Construction Technology under Complex
Geological Conditions Achieved in Guangzhou Metro[J]. Tunnel Construction, 2006
, 26(4)
: 68
-71
.