ISSN 2096-4498
CN 44-1745/U
ISSN 2096-4498
CN 44-1745/U
Excavation and Reinforcement Technology for Foundation
Pits in Saturated Fine Silt Sands
Received date: 2006-03-24
Revised date: 2006-06-06
Online published: 2010-04-21
Sand flowing and piping are prone to occur when construction is performed in ground consisting of saturated fine silt sands. Furthermore, due to the high sensitivity and thixotropy of the ground, ground failure is prone to occur under dynamic actions. In such ground, serious subsidence or collapse will occur if improper construction activities are performed. The article presents the excavation and reinforcement technology adopted for the foundation pit of Jiefang Road Project in Hangzhou, which is situated in saturated fine silt sands.
Key words: foundation pit excavation reinforcement
LIU Kun-Feng
,
GUAN Ze-Yang
. Excavation and Reinforcement Technology for Foundation
Pits in Saturated Fine Silt Sands[J]. Tunnel Construction, 2006
, 26(4)
: 61
-63,67
.
DOI: B
/
| 〈 |
|
〉 |