Analysis on Difficulties and Risks in Construction of Qingchun
Road Rivercrossing Tunnel and Their Countermeasures
Received date: 2006-06-15
Online published: 2010-04-16
Qingchun Road rivercrossing tunnel in Hangzhou is a huge project with largescale construction activities and complicated construction technologies. Due to the numerous uncertain factors, the project involves a large amount of risks. The paper analyzes on the difficulties and risks of unexpected incidents that may occur during the construction of the project under the special geological conditions under Qiantang River and the constraints of the surrounding external environments. Furthermore, the paper studies on the effects of the risk factors on the safety and quality targets set for the project by means of disaster risk evaluation matrix method (R=P C) , by which qualitative evaluations and quantitative analysis are provided. Finally, on basis of the analysis results, the article recommends some countermeasures for the risks. The article can provide basis for further discussions on the fullcourse control of the risks of huge and complicated rivercrossing tunnels.
GAO Jun
,
JIAN Jian-Wen
. Analysis on Difficulties and Risks in Construction of Qingchun
Road Rivercrossing Tunnel and Their Countermeasures[J]. Tunnel Construction, 2006
, 26(5)
: 34
-36,40
.
DOI: B
/
| 〈 |
|
〉 |