 PileBeamArch (PBA) |Construction Technology for Mined Metro Stations

  • SHU Ze-Min
Expand
  • China Railway Erju Co., Ltd.

Received date: 2006-08-28

  Online published: 2010-04-16

Abstract

The paper introduces the construction technology of PileBeamArch (PBA) mehtod applied in the mined North Gongti Road Station of line 10 of Beijing Metro, including the principle and features of PBA method, the construction procedure and the analysis and summary of the key technology. PBA method, which has a good application prospect in the current construction of the Metro works, can be referred to for other similar works in the future.