Breakthrough Clearance Survey of Metro Tunnels
Transferred from Existing Airraid Tunnels

  • WANG Jian
Expand
  • China Railway Tunnel Survey &|Design Institute Co., Ltd.

Received date: 2006-03-24

  Online published: 2009-12-11

Abstract

The existing 7381 airraid tunnel will be used to build Phase 1 project of MRT system in Harbin. The paper presents the contents of the breakthrough clearance survey that is needed in order to transfer the existing airraid tunnel into Metro tunnel. On basis of comparing the measured crosssections with the designed clearance, the paper makes analysis on the results of the breakthrough clearance survey and draws its preliminary conclusion.

Cite this article

WANG Jian . Breakthrough Clearance Survey of Metro Tunnels
Transferred from Existing Airraid Tunnels[J]. Tunnel Construction, 2006
, 26(6) : 28 -29,68 . DOI: A