Machinery Matching and Power Supply Applied in Construction
of Exit Portion of Yuanliangshan Tunnel

  • SHU Yang-Hui
Expand
  • The 2nd Engineering Co., Ltd. of China Railway Tunnel Group

Received date: 2006-06-15

  Revised date: 2006-08-09

  Online published: 2009-12-11

Abstract

The paper presents the construction methods and corresponding machinery matching schemes adopted in each construction stage of exit portion of Yuanliangshan tunnel. On basis of summary of the power capacity of the major electric equipment inside the tunnel, the paper describes the electric matching scheme and the arrangement of the power supply equipment. Finally, regarding the defects in the matching of the machinery and equipment, the paper provides some modification recommendations.