Threebench Sixstep Rapid Construction Technology for
Large Span Tunnels in New Loess Ground
Received date: 2009-06-29
Revised date: 2009-09-14
Online published: 2010-01-04
Taking the construction of the entrance section of Gangcheng tunnel of SJSV bid section on TaiyuanZhongweiYinchuan railway as an example, the authors discuss the rapid construction of tunnels in new loess ground in this paper. Sequential excavation is executed in new loess ground, which minimizes the deformation of the surrounding ground and the primary reinforcement and eliminates the need to install temporary support. In addition, sequential excavation method can solve the traditional problem of restricted working space induced by installing temporary support in new loess ground. The construction scheme is optimized, effective countermeasures are developed, ordinary equipments are allocated, which results in rapid construction of the tunnel in new loess ground.
ZHU Yangjun, YANG Youquan
. Threebench Sixstep Rapid Construction Technology for
Large Span Tunnels in New Loess Ground[J]. Tunnel Construction, 2009
, 29(增刊2)
: 137
-143,210
.
DOI: B
/
| 〈 |
|
〉 |