ISSN 2096-4498

   CN 44-1745/U

二维码
wenzhang

Grouting Technology for Water/sand Leakage Control in No. 2
Vertical Shaft Section of Shenmu Water Transfer Project

Expand
  • Beijing Construction Co., Ltd. of China Railway Tunnel Group, Beijing 100022, China

Received date: 2009-06-29

  Revised date: 2009-09-08

  Online published: 2010-01-04

Abstract

Due to the water/sand leakage encountered at the bottom of No. 2 vertical shaft of Shenmu water transfer project, the vertical shaft is flooded and the construction has to be suspended. In order to solve this problem, grouting method is selected after numerous researches. Various grouting materials are trialed, the grouting techniques are optimized and the difficulty of grouting in 84mdeep vertical shaft under 0.6MPa hydraulic pressure is overcome. The successful sealing of the water/sand leakage improves the construction conditions of the vertical shaft and ensures the successful execution of the following works.

Cite this article

YANG Jianxiong . Grouting Technology for Water/sand Leakage Control in No. 2
Vertical Shaft Section of Shenmu Water Transfer Project[J]. Tunnel Construction, 2009
, 29(增刊2) : 117 -119,188 . DOI: B

Outlines

/

〈 〉