Application of New Construction Technologies in ChiLu Running Tunnel Works on Line 2 of Guangzhou Metro
Received date: 2006-10-31
Revised date: 2006-12-06
Online published: 2010-01-08
Due to the great construction difficulties and high quality requirements of the works, internationallyadvanced shield machines and technologies were introduced to the works and key matching technologies were developed for the works. In the end, the traditional technical problems occurring during the past shieldbored tunnel construction were effectively resolved and a running tunnel with the highest quality in respect of structures, waterproofing and appearance on line 2 of Guangzhou Metro was built. In the paper, the contents and applications of the new construction technologies ( i.e., 1.5m wide segment, EPDM elastic water stops, SLST guidance system, simultaneous grouting and shield type selection) used in the works are described and analysis is made on the economic and social efficiency resulted by the application of the new construction technologies.
XIE Jun-Liang , Zhang-Liang-Hui , Yang-Xiao-Beng . Application of New Construction Technologies in ChiLu Running Tunnel Works on Line 2 of Guangzhou Metro[J]. Tunnel Construction, 2006 , 26(增刊2) : 33 -36 . DOI: B
/
| 〈 |
|
〉 |