ISSN 2096-4498

   CN 44-1745/U

二维码
wenzhang

Construction Technology for Shield Boring through Fractured Zones

  • CENG Wei-Hua
Expand
  • Guangzhou Municipal DunJian Underground Construction Engineering Co., Ltd., Guangzhou 510030, China

Received date: 2006-10-31

  Revised date: 2006-11-14

  Online published: 2010-01-08

Abstract

aking the shield boring through Shougouling fractured zone in TianHua running tunnel of line 3 of Guangzhou Mass Rapid Transit system as example, the author presents the difficulties encountered during the tunnel boring, including buildings protection, mud cakes, water gushing, chamber pressure control and cutting tool damages. Furthermore, the author also provides the corresponding countermeasures.

Cite this article

CENG Wei-Hua . Construction Technology for Shield Boring through Fractured Zones[J]. Tunnel Construction, 2006 , 26(增刊2) : 44 -46 . DOI: B

Outlines

/

〈 〉