Tunnel Boring across underneath Highspeed Railways by Shield Machines

  • LIU Yang-Cheng
Expand
  • Guangzhou Municipal DunJian Underground Construction Engineering Co., Ltd., Guangzhou 510030, China

Received date: 2006-10-31

  Revised date: 2006-11-23

  Online published: 2010-01-08

Abstract

The tunnel boring across underneath the tracks of highspeed railways by shield machines is presented in the paper, with the emphasis being placed on the works conditions, construction difficulties and countermeasure taken in respect of manpower, materials, equipment, boring parameter design and monitoring. The results demonstrate that, with the mentioned countermeasures, the surface subsidence has been effectively controlled and the safety of the railway has been guaranteed.

Cite this article

LIU Yang-Cheng . Tunnel Boring across underneath Highspeed Railways by Shield Machines[J]. Tunnel Construction, 2006 , 26(增刊2) : 47 -49,84 . DOI: B