Design and Construction of the Underground
Circle MRTstation in Downtown

  • CHEN Dun-Rong ,
  • HONG Zheng-Feng
Expand
  • Department of Kaohsiung Mass Rapid Transit, Kaohsiung

Received date: 2007-06-06

  Online published: 2010-04-20

Abstract

The FORMOSA O5/R10 Transfer station, where the KMRT primary routes (the Red and the Orange Lines) meet, is built by 140meter diameter and 27.05m in depth which constructing technology is the hardest of all MRTstations. O5/R10 station used a lot of new constructing methods, for example, circle diaphragm wall by EMX、NEFMAC method (New Fiber Composite Material for Reinforcing Concrete) etc. But those new constructing methods bring the risk and difficulty for construction. Beside, the architecture treatment and special form of entrance designed by wellknown Japanese architect Takamatsu, and the public art in concourse “The Dome of Light” designed by Italian glass art precursor Narcissus Quagliata will highlight the station inspire the passengers.

Cite this article

CHEN Dun-Rong , HONG Zheng-Feng . Design and Construction of the Underground
Circle MRTstation in Downtown[J]. Tunnel Construction, 2007
, 27(增刊) : 486 -493 . DOI: B

Outlines

/

〈 〉