Analysis and Measures for the Wear of Shield Machine Cutters for
Chengdu Metro Line 1

  • LEI Mei-Mao ,
  • ZHOU Bao-Jun
Expand
  • 1. Project Department for Shenzhen Metro Line 5 by Chengtong Company of China
    Railway No. 2 Engineering Group Co., Ltd.,Shenzhen 518083,Guangdong,China;
    2.Wuhan Kingdream Engineering Tool Co., Ltd., Wuhan 410073,China

Received date: 2009-04-07

  Revised date: 2009-04-10

  Online published: 2010-04-06

Abstract

The original cutters of the shield machine is easily worn and eccentrically worn when drilling through the sandy gravel, mudstone and fine sand strata layers where Chengdu Metro Line 1 is located. After a comparison of the relationship between the cutters and the strata, such measures as a replacement of disc cutter by gear cutter and thickening the cutter ring of the common disc cutters are put forward, which have gained good implementation effect.

Cite this article

LEI Mei-Mao , ZHOU Bao-Jun . Analysis and Measures for the Wear of Shield Machine Cutters for
Chengdu Metro Line 1[J]. Tunnel Construction, 2009
, 29(增刊1) : 84 -87 . DOI: A

Outlines

/

〈 〉