隧道建设(中英文) ›› 2019, Vol. 39 ›› Issue (10): 1690-1696.DOI: 10.3973/j.issn.2096-4498.2019.10.016

• 施工技术 • 上一篇    下一篇

无内衬结构竖井盾构快速接收工艺研究

吕波1, 段高翔2, 3   

  1. 1. 中建交通建设集团有限公司, 北京 100142; 2. 中建市政工程有限公司, 北京 100161;3. 中国建筑一局(集团)有限公司, 北京 100161)
  • 收稿日期:2019-02-26 出版日期:2019-10-20 发布日期:2019-12-10
  • 作者简介:吕波(1979—),男,山东济宁人,2002年毕业于长安大学,建筑工程专业,本科,高级工程师,主要从事隧道及地下工程技术研究工作。E-mail: 1392770961@qq.com。

Rapid Receiving Technology for Shield in Shaft without Lining Structure

LYU Bo1, DUAN Gaoxiang2, 3   

  1. (1. China Construction Communications Engineering Group Co., Ltd., Beijing 100142, China; 2. China Construction Municipal Engineering Co., Ltd., Beijing 100161, China; 3. China Construction First Group Co., Ltd., Beijing 100161, China)
  • Received:2019-02-26 Online:2019-10-20 Published:2019-12-10

摘要: 由于车站不能按时提供盾构接收条件,南宁地铁2号线石子塘站—建设路站区间(石建区间)需增设临时接收竖井。按照常规方法,在竖井内衬结构完成后才能进行盾构接收,由此将造成建设工期长、建设成本高、施工工序多等问题。为解决以上问题,通过采取加大并密排对应盾构进入接收竖井位置的围护桩、以水平环梁代替对撑或外拉锚、在洞门位置用玻璃纤维筋代替钢筋、采用特制的洞门密封装置、灵活设置临时封底、优化接收前盾构掘进参数,并辅以降水、监测等措施,不必施作竖井内衬结构,盾构直接切削桩体进入竖井,安全、快速地实现了盾构接收,为石建区间按时贯通提供了保障。

关键词: 盾构接收, 无内衬竖井, 结构设计

Abstract: Due to the fact that the station cannot provide the shield receiving conditions on time, a temporary receiving shaft should be added to Shizitang StationJianshe Road Station Section on Nanning Metro Line 2. According to the conventional method, the shield can be received after the shaft lining structure is completed, which will cause problems such as long construction period, high construction cost and multiple construction procedures. Hence, in order to solve the abovementioned problems, a series of technologies, i.e. adopting enlarged and closepacked piles at the position of shield machine entering the receiving shaft, replacing the support or the outer pull anchor by horizontal ring beam, using the glass fiber rib instead of the steel bar at the tunnel portal, using special sealing device for tunnel portal, flexible setting of the temporary sealing bottom, optimization of the tunneling parameters before shield receiving, and the precipitation, monitoring and other measures, are adopted. The shield machine can directly cut the pile into the shaft without the need to apply the shaft lining structure, and the shield receiving has been realized safely and quickly, which can provide guarantee for the completion of the project.

Key words: shield receiving, shaft without lining, structural design