摘要: 为研究复杂艰险铁路隧道的成本控制问题,通过对部分隧道工程成本数据进行分析,总结出铁路复杂艰险隧道〖JP〗工程成本存在亏损情况突出、超长工期工程亏损严重、亏损呈现地区性等突出问题,并从工程技术、工程经济、工程管理、宏观政策等方面分析影响工程成本的主要因素,提出依法合规调整在建工程价款、尽量避免签订无限风险合同等工程成本管理建议。
关键词: 铁路隧道, 工程造价, 造价影响因素, 成本管理
Abstract: In order to better control the cost of complex and difficult railway tunnels, the cost data of some tunnel projects are analyzed. It is found that the complex and difficult tunnel projects are always characterized by serious cost loss, serious loss of overlong construction period and regional loss. And then, the main factors affecting engineering cost are summarized from 4 aspects, i.e. engineering technology, engineering economy, engineering management and macro policy. Finally, suggestions, i.e. adjusting the cost of project in construction according to laws and regulations, and avoiding signing contracts with unlimited risks are put forward.
Key words: railway tunnel, construction cost, cost influencing factors, cost control
中图分类号:
U 45
何英南. 铁路复杂艰险隧道的成本影响因素分析[J]. 隧道建设, 2020, 40(9): 1279-1284.
HE Yingnan. Study of Cost Influencing Factors of Complex and Difficult Railway Tunnels[J]. Tunnel Construction, 2020, 40(9): 1279-1284.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://www.suidaojs.com/CN/10.3973/j.issn.2096-4498.2020.09.005
http://www.suidaojs.com/CN/Y2020/V40/I9/1279
地铁盾构隧道近接下穿既有铁路隧道加固范围优化设计——以南宁地铁4号线下穿既有槎路隧道为例
铁路隧道巨型溶洞深厚回填体注浆固结技术——以黔张常铁路高山隧道为例