隧道建设(中英文) ›› 2023, Vol. 43 ›› Issue (S1): 480-486.DOI: 10.3973/j.issn.2096-4498.2023.S1.056

• 施工技术 • 上一篇    下一篇

TBM法隧道仰拱同步现浇施工技术与装备研制

徐鹏祖1, 2, 杨延栋2, 3 *, 徐海峰1, 2, 刘万林4, 王天一3   

  1. 1. 中铁隧道股份有限公司, 河南 郑州 450001 2. 中铁隧道局集团有限公司,广东 广州 511458; 3. 盾构及掘进技术国家重点实验室, 河南 郑州 450001;4. 中铁开发投资集团有限公司, 云南 昆明 650118)

  • 出版日期:2023-07-31 发布日期:2023-08-28
  • 作者简介:徐鹏祖(1986—),男,甘肃会宁人,2010年毕业于白城师范学院,土木工程专业,本科,高级工程师,现从事TBM法隧道施工与管理工作。 Email: 517038370@qq.com。 *通信作者: 杨延栋, Email: yay_sky@163.com。

Synchronous CastinPlace Construction Technology and Equipment Development for TBM Tunnel Invert Arch

XU Pengzu1, 2, YANG Yandong2, 3, *, XU Haifeng1, 2, LIU Wanlin4, WANG Tianyi3   

  1. (1. China Railway Tunnel Stock Co., Ltd., Zhengzhou 450001, Henan, China; 2. China Railway Tunnel Group Co., Ltd., Guangzhou 511458, Guangdong, China; 3. State Key Laboratory of Shield Machine and Boring Technology, Zhengzhou 450001, Henan, China; 4. Railway Development Investment Group Co., Ltd., Kunming 650118, Yunnan, China)

  • Online:2023-07-31 Published:2023-08-28

摘要: 为解决现浇仰拱衬砌阻断物料运输通道难以与TBM掘进同步实施的工程难题,通过分析与比选提出带承台平面仰拱设计方案,研制由爬坡轨、U型主梁、分段支撑、步进移位、仰拱模板等系统构成的TBM法隧道仰拱同步现浇衬砌台车,开发由轨道轨枕拆除、隧底清渣、钢筋绑扎、仰拱浇筑、仰拱养护、轨道安装等工序组成的仰拱同步现浇施工工艺。在滇中引水香炉山隧洞得到成功应用。仰拱现浇衬砌不影响TBM正常施工,单仓24 m现浇仰拱作业循环时间44 h,施工进度可达200 m/月,实现了仰拱现浇与TBM掘进的同步高效作业。

关键词: 仰拱衬砌, 同步现浇, 衬砌台车, 超长隧道, 滇中引水

Abstract:

To realize synchronous implementation of tunnel boring machine(TBM) excavation and construction material transportation during invert arch castinplace construction, a design scheme of plane invert arch with bearing platform is proposed through analysis and comparison. Additionally, a synchronous castinplace lining trolley for TBM tunnel invert arch integrating climbing rail, Ushaped main beam, segmented support, stepping shift, and invert arch formwork is developed. Finally, a series of synchronous castinplace techniques for invert arch are developed, which includes track demolition, tunnel bottom muck cleaning, steel bar binding, invert arch casting and maintenance, and track installation. The scheme, trolley, and techniques mentioned have been successfully applied in Xianglushan tunnel of Central Yunnan water diversion project. The castinplace lining of invert arch did not affect the normal construction of TBM. The operation cycle time of 24 m castinplace invert arch in a single warehouse was 44 h, and the construction progress reached 200 m a month, realizing synchronous and efficient operation of invert arch castinplace construction and TBM tunneling, which is worth popularizing.

Key words: invert arch lining, synchronous castinplace, lining trolley, superlong tunnel, Central Yunnan water diversion project