Tunneling in Mud/Sand Bursting Geology by Singleshield TBM

GAO Kun   

  1. (China Railway Tunnel Stock Co., Ltd., Zhengzhou 450001, China)
  • Received:2011-11-15 Revised:2011-12-30 Online:2012-02-20 Published:2012-03-09

Abstract: No. 7 tunnel of the first phase of Tao River Diversion Project in Gansu Province is excavated by a singleshield TBM. During the construction of the tunnel, water/mud/sand bursting occurs. Countermeasures, including advance geology prediction, backfilling grouting for gaps behind the segment, advance consolidation grouting and water/sand releasing after diluting, are taken to cope with the situation. 

Key words: singleshield TBM, mud/sand bursting, tunnel