The primary support deformation of unsymmetricallypressured tunnels in Funiushan area is serious. As a result, study is carried out on deformation causes, main countermeasures and construction organization. The deformation of the primary support is analyzed in terms of geophysical prospecting, drilling, test, monitoring and numerical simulation; the analytical results are compared to actual conditions; and the original design of primary support parameters is regarded as the main causes of primary support cracks. Thus countermeasures, i.e. improvement of steel frame, adding systematic anchor bolts and grouting behind primary support, are adopted based on existing primary support technology; construction organization methods, i.e. short bench, short advance, rapid ring closure and timely inverted arch lining, are used. The primary support deformation has been successfully controlled and the construction safety of the tunnel has been guaranteed by adopting abovementioned technologies.
Key words: Mawan Tunnel, unsymmetrical pressure, primary support deformation, deformation analysis, parameter optimization
CLC Number:
U 45
ZONG Shuhe, CHU Yuyong. Deformation Cause Analysis and Parameter Optimization of Primary Support of Shallowburied Unsymmetricallypressured Section of Mawan Tunnel[J]. Tunnel Construction, 2017, 37(S2): 211-217.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.2096-4498.2017.S2.032
http://www.suidaojs.com/EN/Y2017/V37/IS2/211