ISSN 2096-4498

   CN 44-1745/U

二维码

Tunnel Construction ›› 2021, Vol. 41 ›› Issue (8): 1385-.DOI: 10.3973/j.issn.2096-4498.2021.08.015

Previous Articles     Next Articles

Construction Technology Innovation of Double-Shield Tunnel Boring -Machine in Qingdao Metro Line 1

GUO Zhi1, QU Qiufen2, FAN Zhiguo1, LIU Guitao1, LU Xiaofeng1, GONG Yinglei1   

  1. (1. CSSC (Qingdao) Rail Transit Equipment Co., Ltd., Qingdao 266111, Shandong, China; 2. Romay (Qingdao) Co., Ltd., Qingdao 266108, Shandong, China)
  • Online:2021-08-20 Published:2021-09-06

Abstract: When a doubleshield tunnel boring machine (TBM) is applied in urban rail transit, there are always several limitations, such as no condition for launching shaft construction, low construction efficiency due to doubletrack smallspacing excavation and frequent station passing, and low economic benefit. Accordingly, a case study is conducted on Qingdao metro line 1. Further, the applicable experience of doubleshield TBM used in Qingdao metro line 2 is studied, and detailed conditions of line 1 and the TBM characteristics are analyzed; thus, a suite of negative ring launching techniques of doubleshield TBM based on tunneling mode, parameters, and attitude control is developed. The techniques include doubletrack smallspacing tunnel excavation realized by a movable support trolley installed in the advance tunnel and Soletanche grouting reinforcement and backup trolley stationpassing technology realized by precast steel support replacement. The application of the techniques shows a good effect in Qingdao metro line 1.

Key words: doubleshield tunnel boring machine, negative ring launching, smallspacing tunnel, precast steel support, station crossing

CLC Number: